Ivegill Road closure update - January 2025

Road Patching

Ivegill Road Closure Update – January 2025

The closure of Ivegill Road remains necessary in order to complete the utility diversions and the ongoing challenges in this section of the project. 

The civil engineering elements of the project will commence following the completion of the utility diversions outlined below. This includes the construction of the remaining part of the new culvert and beginning the engineering works to build the embankment for the new realigned Ivegill Road. 

Collaborative efforts between Electricity North West (ENW), United Utilities (UU), BT, and our contractor Galliford Try have focused on ensuring safety and progress despite unexpected issues such as challenging ground conditions and uncharted utilities.
 
Here’s an updated timeline of works:  

  • • ENW works are now complete.   
  • • United Utilities will begin road crossings and connections on 20 January 2025.
  • • BT will commence cabling works on 3 February 2025.


The road will reopen in May 2025.  

We thank you for your patience and understanding as we work to reopen Ivegill Road and prioritise the safety of all involved.  

If you have any questions, please contact carlislesouthernlinkroad@cumberland.gov.uk