Cumberland Council would like to provide an update for the ongoing road improvements on the A5086 Cockermouth.
This ambitious project will enhance the local road network and ensure safer, smoother travel for residents and businesses.
The planned improvements on the A5086 at Cockermouth include road network repairs, drainage system replacement, traffic sign upgrades, and a refresh of road markings. To complete these essential upgrades efficiently and safely, the project will continue with the following updated phases:
- Phase 3 The Level – road closure and traffic lights, continues until Monday 24 March.
- Phase 4 Main Street roundabout – Tuesday 25 March to Wednesday 26 March – road closure at Gallowbarrow with two-way traffic lights at Main Street roundabout – access to Town Centre from Crown Street.
- Phase 5 The Level traffic lights – Thursday 27 March to Friday 28 March –road closure from 6.30pm – 12.00am, in quieter hours.
Full access will be available for emergency service vehicles, pedestrians, and dismounted cyclists throughout the works.
Waste and recycling collections will proceed as usual, while updates about temporary bus stop relocations will be posted at affected stops. Passengers with bus route questions are encouraged to contact Stagecoach directly.
Cumberland Council recognises that the A5086 is a key route, and some temporary inconvenience may occur during these works. The council is working closely with local stakeholders, including Parish Councils and local members, to reduce disruption as much as possible.
Cumberland Council wishes to thank the community for their continued support and patience while they improve the road network and apologise for any inconvenience.
If you have any questions, you can visit Cumberland Council website, or contact Cumberland Council’s Highways Hotline on 0300 373 3736