Devonshire Street

The scheme, funded by the UK Government’s Future High Street Fund aims to increase the space for pedestrians and businesses.

Project overview


In order to achieve the project objectives of improving the area for local residents and businesses, the proposals for the Devonshire Street include: 

  • widening the pavements on both sides of the road
  • introduction of new seating, trees, and plants
  • providing cycle racks
  • single lane carriageway for vehicles
  • two loading bays

In order to do this, we are proposing to:

  • remove the existing bus stops and bus lane
  • relocate a bus stop on to Victoria Viaduct
  • remove the existing temporary cycle lane

An artist impression of the proposed changes to Devonshire Street

Image
Artist impression of the proposed changes to Devonshire Street

Overhead plan and dimensions

This image is a visual of the plan for the area, on this image you can see the extent of all the proposed changes to Devonshire Street and English Street.

Image
Visual providing full layout of Devonshire Street and English Street

The image below provides the dimensions for a cross section of Devonshire street.

Image
Visual providing measurements and layout of Devonshire Street

Programme

The timeline for this project is as follows:

  • June 2023 - Consultation
  • July 2023 - Technical design
  • October 2023 - Traffic Regulation Order
  • November 2023 - Construction
  • Summer 2024 - Construction complete