The scheme, funded by the UK Government’s Town Deal Fund, aims to improve the area for pedestrians, cyclists and people using this area of the city.
The proposals for the English Street project include:
- widening the pavements
- introduction of new seating, trees, and planting to encourage pollinators.
- bi-directional cycle lane – the first stage of a new cycle network planned for the city centre.
- providing cycle racks
- new raised crossing points for pedestrians
- single lane carriageway for vehicles with a separate lane to turn on to Devonshire Street
- three bus stops
To do this, we are proposing to:
- remove two of the five current bus stops
- relocate a bus stop on to Victoria Viaduct
- remove some of the existing loading and taxi ranks (space will remain outside the new University building)
An artist impression of the proposed changes to English Street
Overhead plan and dimensions
Here is a visual of the plan for the area, on this image you can see the extent of all the proposed changes to Devonshire Street and English Street.
The image below provides some dimensions for a cross section of English Street.
Programme
- June 2023 - Consultation
- September 2023 - Technical Design
- October 2023 - Traffic Regulation Order
- Spring 2024 - Construction
- Winter 2025 - Construction Complete